Home Finance – determines loan requirements, income, CDIB, credit, and loan amount
Forwards loan commitment to Modular Customer Relations
Contacts homeowners after they have been approved
Requests an Environmental review to begin process
Contact customers that they have been approved
Get customer information and driving directions to home site
Evaluate site to note any obstacles for house move
Contacts city/county code enforcement restrictions and / or permits
Apply for Grossman & Keith bridge study
Explains finds on customer’s home site as possibility of: (tree removal, new driveways added, easements and fence removal)
Forwards information to Home Finance
Requests and receives a copy of the survey and perk from Finance Department
Supplies customer with utility commitment letters that must be completed by utility companies
Make sure utility commitment letters are turned into modular plant with survey and perk test that precedes the following
Check Availability for water, city, rural or well
Sewer availability - tie in, new system, or lagoon (2.5 acres minimum)
Make sure utility deposits are paid by the customer before proceeding
Develop planning budget for home, site, and land development to be forwarded to home finance
Provide available floor plans and sample selections for customer to choose from
Forward customer selections to home finance for appraisal
Customer signs for filing the Useful Life/Deed Restriction
Proceed to order materials after the customer closes on the loan after the environmental is complete
Requested bids and returned for requisitions for procurement
Received purchase order and then materials are ordered pending delivery
Materials delivered banded and stored in the modular plant to begin construction
Requisition the tap fees
Framing: Flooring / Sub Flooring
Flooring / Sub Flooring
Wall Sheathing
Roof Sheathing
Trusses
Finishing Roof
Window / Exterior Doors
Electrical Rough-In
Plumbing Rough-In
HVAC Rough-In
Insulation
Exterior doors and windows
Exterior Siding
Sheetrock: Tape/bed/texture (begin process for site work)*
Request bids for dirt, rebar, concrete, septic and underground electric*
Interior: Trim and millwork
Interior doors
Hardware
Interior paint
Cabinetry
Floor Coverings
Vinyl and Carpet Installed
Load the house to move it
Apply for the final Grossman and Keith bridge study
Apply for DOT approval to move house
Notify Okie to locate underground utility lines
Notify contractors to set up a time for concrete and fill dirt to be delivered
Footings completed
Pre-Treat ordered
Permit received then can continue to schedule move
Schedule move according to DOT’s permit
Coordinate with utility companies for connections
Licensed plumbers, electricians and HVAC work simultaneously with finishing crew***
Cabinetry – Finish
Porches complete
Final cleaning of the house
Finalize for move in
Sewer and Septic work completed
Plumbing Final – Out
HVAC Final – Out
Electrical Final - Out
A year end inspection will be scheduled
Homeowner, plant foreman, development specialist will meet and discuss potential warranty issues, if any
Assessment and completion of year end problems will be completed by finishing crew
Homeowner will then sign agreement when they are satisfied with year-end.